STEREO Weekly Meeting Minutes for 2008-09-23 (Week 39) ANNOUNCEMENTS ------------- * None. INSTRUMENT AND SPACECRAFT STATUS -------------------------------- * All subsystems on both spacecraft are nominal, except that the Ahead spececraft is currently operating on IMU #2. DISCUSSION AND OPERATIONS CONSTRAINTS ------------------------------------- Week 38 * The IMPACT team uploaded a LET software patch to Ahead on day 259 (Sep 15). The LET team reports that the patch looks good. * The 16th momentum dump on Ahead occured on day 260 (Sep 16) at 13:00 UT. * There was a power outage at station 25 during the Behind pass on day 261 (Sep 17). This resulted in a loss of about 45 minutes of data for all instruments. * The station 24 support for Behind scheduled for day 263 (Sep 19) was cancelled on day 261 (Sep 17) because the receiver was red. Station 26 was scheduled instead, at a slightly different start time. * Behind switched to 480 kbps on Sep 15. * The SECCHI team uploaded flight software patch 5.09 to Behind on Monday, day 260 (Sep 15). * The average daily downlink was 7.2 gigabits on Ahead, and 6.9 gigabits on Behind. Week 39 * A return-to-service track on Behind, and a PIT test, was carried out yesterday (Sep 22) on station 24. No SSR playback was performed during this track. In spite of some weather issues, the track was carried out successfully. * The 11th momentum dump on Behind is occuring today (Sep 23) at 17:00 UT. Week 40 * The SECCHI stepped calibration roll on Ahead is scheduled for day 274 (Sep 30) at 06:55 UT. Week 41 * There will be a MESSENGER fly-by of Mercury on Monday, October 6. Week 42 * Ahead will switch to 480 kbps on Oct 13. Other * There was some discussion of a limit check that occured on PLASTIC during the momentum dump. This was related to cycling power on the entrance system, and is normal. * SECCHI reports that they've been seeing a larger than usual change recently in the Attitude History files between versions 1 and 3 on Ahead. * SECCHI also reports that they're missing image telemetry for Ahead for several hours on Aug 27. However, there are no gaps in the housekeeping telemetry. As far as they know, they were taking images during this period, and don't know why the telemetry is missing. COORDINATED OBSERVATIONS ------------------------ ------------------------------------------------------------------------------- Scheduled activities for Week 39: M Sep 22 (266) T Sep 23 (267) Behind: Momentum dump, 17:00 UT W Sep 24 (268) T Sep 25 (269) F Sep 26 (270) S Sep 27 (271) S Sep 28 (272) Notes: * Sep 20-Oct4 SUMER Mini-campaign ------------------------------------------------------------------------------- Scheduled activities for Week 40: M Sep 29 (273) T Sep 30 (274) Ahead: SECCHI stepped calibration roll, 06:55 UT W Oct 01 (275) T Oct 02 (276) F Oct 03 (277) S Oct 04 (278) S Oct 05 (279) Notes: * Sep 20-Oct4 SUMER Mini-campaign ------------------------------------------------------------------------------- Scheduled activities for Week 41: M Oct 06 (280) Messenger - Mercury fly-by T Oct 07 (281) W Oct 08 (282) T Oct 09 (283) F Oct 10 (284) S Oct 11 (285) S Oct 12 (286) ------------------------------------------------------------------------------- Scheduled activities for Week 42: M Oct 13 (287) Ahead: Switch downlink rate to 480 kbps T Oct 14 (288) W Oct 15 (289) T Oct 16 (290) JOP 80, EIT shutterless F Oct 17 (291) S Oct 18 (292) S Oct 19 (293) ------------------------------------------------------------------------------- Upcoming events: 2008: SECCHI Stepped calibration rolls Ahead: Dec 16 Behind: Dec 2 ICAL-001: Sep 1-5, Oct 6-10, Nov 3-7, Dec 1-5 * Oct 16,28 JOP 80, EIT shutterless * Nov 1-Dec 15 SUMER campaign (may be cancelled) 2009: ICAL-001: Jan 5-9, Jan 26-30, Mar 2-6 SECCHI Stepped calibration rolls Ahead: Mar 10, Jun 9, Sep 2, Nov 24 Behind: Mar 10, Jun 16, Sep 22, Dec 22 * Jan 15,22 JOP 80, EIT shutterless * May 18 Ahead: Switch downlink rate to 360 kbps * Jun 8 Behind: Switch downlink rate to 360 kbps * Aug 4 Both: Increase track duration from 4 to 5 hours * Aug 10 Ahead: Switch downlink rate to 160 kbps * Aug 31 Behind: Switch downlink rate to 160 kbps * Sep 10 Ahead at L4 Lagrange point * Sep 29 Messenger - Mercury fly-by * Oct 25 Behind at L5 Lagrange point