------------------------------------------------------------------------------- Scheduled activities for Week 43: M Oct 23 (296) T Oct 24 (297) W Oct 25 (298) T Oct 26 (299) Launch (00:52 UT; 8:52 EDT 25 October) F Oct 27 (300) Power on SECCHI, move doors from superclosed to closed Power on SWAVES Ahead: Deploy SWAVES antennas S Oct 28 (301) 1st Engineering Burn Power on IMPACT IDPU, SWEA, STE, Deploy SWEA cover Power on PLASTIC S Oct 29 (302) Power on IMPACT/SWEA HVPS Behind: Deploy SWAVES antennas ------------------------------------------------------------------------------- Scheduled activities for Week 44: M Oct 30 (303) A1 Prime Delta V Maneuver T Oct 31 (304) A1 Apogee W Nov 01 (305) Deploy IMPACT boom T Nov 02 (306) 2nd Engineering Burn F Nov 03 (307) S Nov 04 (308) S Nov 05 (309) ------------------------------------------------------------------------------- Scheduled activities for Week 45: M Nov 06 (310) P1 Perigee Ahead: EA mode test Ahead: SECCHI mechanism spin test 21:18 T Nov 07 (311) W Nov 08 (312) T Nov 09 (313) Behind: SECCHI mechanism spin test 22:25 F Nov 10 (314) Behind: SECCHI mechanism spin test 14:15 S Nov 11 (315) Ahead: 1st enabling of GT use A2 Apogee S Nov 12 (316) ------------------------------------------------------------------------------- Scheduled activities for Week 46: M Nov 13 (317) Behind: 1st enabling of GT use Power up IMPACT SEP T Nov 14 (318) A2+ Prime Delta V Maneuver W Nov 15 (319) T Nov 16 (320) F Nov 17 (321) P2 Perigee & Delta V Maneuver S Nov 18 (322) S Nov 19 (323) ------------------------------------------------------------------------------- Scheduled activities for Week 47: M Nov 20 (324) IMPACT MAG rolls, HGA end-to-end slew Behind: SECCHI mechanism spin test 20:50 T Nov 21 (325) W Nov 22 (326) T Nov 23 (327) A3 Apogee F Nov 24 (328) S Nov 25 (329) S Nov 26 (330) Notes: * Some telemetry was lost this week because of overloaded buffers. ------------------------------------------------------------------------------- Scheduled activities for Week 48: M Nov 27 (331) T Nov 28 (332) W Nov 29 (333) P3 Perigee IMPACT MAG rolls, HGA end-to-end slew T Nov 30 (334) SECCHI mechanism spin tests (A: 00:00, B: 00:06,13:52) F Dec 01 (335) S Dec 02 (336) S Dec 03 (337) ------------------------------------------------------------------------------- Scheduled activities for Week 49: M Dec 04 (338) Ahead: Open EUVI, COR1, & COR2 doors, first light T Dec 05 (339) W Dec 06 (340) A4 Apogee Ahead: 2nd GT Calibration (performed with incorrect tables) Behind: A4 Prime Delta V Maneuver T Dec 07 (341) Start space weather beacon broadcast post-track F Dec 08 (342) S Dec 09 (343) S Dec 10 (344) ------------------------------------------------------------------------------- Scheduled activities for Week 50: M Dec 11 (345) Ahead: Power test, 45 degree off-point Both: Stop space weather beacon broadcast post-track T Dec 12 (346) P4 Perigee, IMPACT MAG rolls, HGA end-to-end slew Auto track on HGA test W Dec 13 (347) Ahead: Momentum Dump 13:00 UT Ahead: Open HI baffle cover door, first light Behind: Open EUVI, COR1, & COR2 doors, first light Both: Restart space weather beacon broadcast post-track T Dec 14 (348) Ahead: SECCHI GT calibration 14:00 UT Ahead: Open IMPACT SIT and SEPT covers F Dec 15 (349) S1 first lunar swingby S Dec 16 (350) Behind: SECCHI GT Calibration S Dec 17 (351) ------------------------------------------------------------------------------- Scheduled activities for Week 51: M Dec 18 (352) Ahead: First SWAVES smooth calibration rolls T Dec 19 (353) Behind: First SWAVES smooth calibration rolls Both: SECCHI mechanism spin tests (A: 17:41, B: 13:35) W Dec 20 (354) Ahead: Second SWAVES smooth calibration rolls 07:20 UT Behind: SECCHI GT calibration 20:00 UT Ahead: HGA calibration T Dec 21 (355) Ahead: SECCHI GT calibration 12:00 UT Behind: SECCHI GT calibration 11:05 UT Behind: S1+ Prime Delta V Maneuver Ahead: HGA calibration Both: SECCHI mechanism spin tests (A: 15:25, B: 00:18) F Dec 22 (356) S Dec 23 (357) Ahead: Third SWAVES smooth calibration rolls 07:20 UT S Dec 24 (358) ------------------------------------------------------------------------------- Scheduled activities for Week 52: M Dec 25 (359) T Dec 26 (360) Ahead: SECCHI GT calibration Behind: SECCHI software load W Dec 27 (361) T Dec 28 (362) F Dec 29 (363) S Dec 30 (364) S Dec 31 (365) -------------------------------------------------------------------------------