Instrument Milestones

Project Start Date: 11/1/02

Project End Date: 10/31/04

File Name: c:\STEREO\Bnets\SummaryCharts\2003_05_31_IMPACT STE Instrument Critical Milestone Chart.ML7

ITEM EVENT Require Action
1 FM 1 Detector PWB Fabricated
2/12/03 7/21/03
2 FM 2 Detector PWB Fabricated
2/12/03 7/21/03
3 ETU Detector Board Loaded
2/13/03 4/4/03
4 ETU Detector PWB Tested
2/28/03 4/18/03
5 Flight Detector PWBs Coupon Tested
3/6/03 8/11/03
6 Long Lead Parts Procured and Screened
3/31/03 6/27/03
7 FM 1 Detector Board Loaded
4/10/03 9/2/03
8 FM 1 Detector PWB Tested
4/23/03 9/15/03
9 ETU I & T Complete
4/24/03 6/12/03
10 STE ETU Complete
4/24/03 6/12/03
11 Flight Detectors Received
8/11/03 9/16/03
12 Flight Detectors Tested
9/5/03 10/13/03
13 FM 1 I & T Complete
10/2/03 10/13/03
14 FM 1 Calibrated
10/31/03 11/11/03
15 FM 1 Enviornmental Testing Complete
12/8/03 12/16/03
16 FM 2 Detector Board Loaded
10/7/03 12/19/03
17 Deliver STE-D FM 1 For SWEA/STE I & T
12/16/03 12/19/03
18 FM 2 Detector PWB Tested
10/21/03 1/6/04
19 Deliver STE-U FM 1
1/7/04 1/8/04
20 FM 2 I & T Complete
1/21/04 1/29/04
21 FM 2 Calibrated
12/8/03 2/25/04
22 Deliver STE-D FM 2 For SWEA/STE I & T
1/6/04 3/23/04
23 FM 2 Enviornmental Testing Complete
1/6/04 3/23/04
24 Deliver STE-U FM 2
4/19/04