Instrument Milestones

Project Start Date: 11/1/02

Project End Date: 10/31/04

File Name: c:\STEREO\Bnets\SummaryCharts\2003_05_31_IMPACT SSI Instrument Critical Milestone Chart.ML7

ITEM EVENT Require Action
1 STE Weak Radiation Source Paperwork Processed
2/3/03 6/2/03
2 FM 1 SWEA Baseplate Fabricated
2/20/03 6/18/03
3 FM 2 SWEA Baseplate Fabricated
2/24/03 6/20/03
4 Deliver SWEA/STE-D ETU For IDPU I & T
5/2/03 6/27/03
5 STE-D FM 1 Preamp PWB Fabricated
7/14/03 9/8/03
6 STE-D FM 2 Preamp PWB Fabricated
7/14/03 9/8/03
7 STE-D FM 1 Shaper PWB Fabricated
7/15/03 9/9/03
8 STE-D FM 2 Shaper PWB Fabricated
7/15/03 9/9/03
9 STE-D FM 1 Preamp PWB Loaded
8/11/03 10/7/03
10 STE-D FM 2 Preamp PWB Loaded
8/11/03 10/7/03
11 STE-D FM 1 Shaper PWB Loaded
8/11/03 10/7/03
12 STE-D FM 2 Shaper PWB Loaded
8/11/03 10/7/03
13 Deliver FM 1 STE-U I/F for I & T
9/17/03 11/13/03
14 Deliver FM 2 STE-U I/F for I & T
10/16/03 12/12/03
15 Deliver SWEA/STE-D For Suite I & T
1/28/04 2/23/04
16 Deliver SWEA/STE-D For Suite I & T
5/3/04 5/4/04

SSI001.png

SSI002.png