ITEM | EVENT | Require Action | ||
---|---|---|---|---|
1 | STE Weak Radiation Source Paperwork Processed | 2/3/03 | 6/2/03 | |
2 | FM 1 SWEA Baseplate Fabricated | 2/20/03 | 6/18/03 | |
3 | FM 2 SWEA Baseplate Fabricated | 2/24/03 | 6/20/03 | |
4 | Deliver SWEA/STE-D ETU For IDPU I & T | 5/2/03 | 6/27/03 | |
5 | STE-D FM 1 Preamp PWB Fabricated | 7/14/03 | 9/8/03 | |
6 | STE-D FM 2 Preamp PWB Fabricated | 7/14/03 | 9/8/03 | |
7 | STE-D FM 1 Shaper PWB Fabricated | 7/15/03 | 9/9/03 | |
8 | STE-D FM 2 Shaper PWB Fabricated | 7/15/03 | 9/9/03 | |
9 | STE-D FM 1 Preamp PWB Loaded | 8/11/03 | 10/7/03 | |
10 | STE-D FM 2 Preamp PWB Loaded | 8/11/03 | 10/7/03 | |
11 | STE-D FM 1 Shaper PWB Loaded | 8/11/03 | 10/7/03 | |
12 | STE-D FM 2 Shaper PWB Loaded | 8/11/03 | 10/7/03 | |
13 | Deliver FM 1 STE-U I/F for I & T | 9/17/03 | 11/13/03 | |
14 | Deliver FM 2 STE-U I/F for I & T | 10/16/03 | 12/12/03 | |
15 | Deliver SWEA/STE-D For Suite I & T | 1/28/04 | 2/23/04 | |
16 | Deliver SWEA/STE-D For Suite I & T | 5/3/04 | 5/4/04 |