| ITEM | EVENT | Require Action | ||
|---|---|---|---|---|
| 1 | FM 1 Door Fabricated | 3/10/03 | 7/7/03 | |
| 2 | FM 2 Door Fabricated | 3/10/03 | 7/7/03 | |
| 3 | FM 1 Housing Fabricated | 3/17/03 | 7/14/03 | |
| 4 | FM 1 Electronics Enclosure Fabricated | 3/17/03 | 7/14/03 | |
| 5 | FM 2 Housing Fabricated | 3/17/03 | 7/14/03 | |
| 6 | FM 2 Electronics Enclosure Fabricated | 3/17/03 | 7/14/03 | |
| 7 | FM 1 Energy Board Fabricated | 3/18/03 | 5/8/03 | |
| 8 | FM 2 Energy Board Fabricated | 3/18/03 | 5/8/03 | |
| 9 | FM 1 HVPS Available | 3/31/03 | 6/30/03 | |
| 10 | Flight Logic Boards Fabricated | 4/8/03 | 6/27/03 | |
| 11 | FM 1 Telescope Assembled | 4/11/03 | 8/8/03 | |
| 12 | FM 2 Telescope Assembled | 4/11/03 | 8/8/03 | |
| 13 | FM 1 Energy Board Assembled | 4/21/03 | 6/12/03 | |
| 14 | FM 2 Energy Board Assembled | 4/21/03 | 6/12/03 | |
| 15 | Flight Mother Boards Fabricated | 4/21/03 | 5/30/03 | |
| 16 | On-board Flight S/W Validated | 4/25/03 | 7/11/03 | |
| 17 | FM 1 Energy Board Tested | 5/12/03 | 7/3/03 | |
| 18 | FM 1 Logic Board Assembled w/ETU ACTEL | 5/13/03 | 8/4/03 | |
| 19 | FM 2 Logic Board Assembled w/ETU ACTEL | 5/13/03 | 8/4/03 | |
| 20 | Flight Mother Boards Assembled | 5/23/03 | 6/27/03 | |
| 21 | FM 1 Mother Board Functionally Tested | 6/2/03 | 7/7/03 | |
| 22 | FM 2 Energy Board Tested | 6/3/03 | 7/25/03 | |
| 23 | FM 1 Logic Board w/ETU ACTEL Functionally Tested | 6/4/03 | 8/25/03 | |
| 24 | FM 1 HVPS Funtionally Tested | 6/9/03 | 7/14/03 | |
| 25 | Deliver EM for SEP EM I & T | 6/13/03 | ||
| 26 | FM 1 Telescope Fit Tested | 6/16/03 | 8/12/03 | |
| 27 | FM 2 Logic Board w/ETU ACTEL Functionally Tested | 6/25/03 | 9/16/03 | |
| 28 | FM 2 Mother Board Functionally Tested | 6/27/03 | 9/18/03 | |
| 29 | FM 1 Digital TOF Boards Available | 7/21/03 | 8/18/03 | |
| 30 | FM 2 Digital TOF Boards Available | 7/28/03 | 8/18/03 | |
| 31 | FM 2 Analog TOF Boards Available | 7/28/03 | 8/18/03 | |
| 32 | FM 1 Analog TOF Boards Available | 7/28/03 | 8/18/03 | |
| 33 | FM 2 HVPS Available | 8/5/03 | 9/9/03 | |
| 34 | FM 1 TOF Boards Functional Test Complete | 8/11/03 | ||
| 35 | FM 2 HVPS Functionally Tested | 8/12/03 | 9/25/03 | |
| 36 | FM 1 Integrated | 8/13/03 | 8/27/03 | |
| 37 | FM 2 Telescope Fit Tested | 8/19/03 | 10/2/03 | |
| 38 | FM 2 TOF Boards Functional Test Complete | 8/26/03 | 8/29/03 | |
| 39 | FM 2 Integrated | 8/28/03 | 10/7/03 | |
| 40 | FM 2 Tested | 10/3/03 | 11/12/03 | |
| 41 | FM 2 Environmentally Tested | 10/27/03 | 12/4/03 | |
| 42 | FM 1 Environmentallyl Tested | 12/16/03 | 12/31/03 | |
| 43 | FM 1 Logic Board Assembled w/Flight ACTEL | 12/23/03 | 1/8/04 | |
| 44 | FM 2 Logic Board Assembled w/Flight ACTEL | 12/23/03 | 1/8/04 | |
| 45 | FM 1 Logic Board w/Flight ACTEL Functionally Tested | 12/26/03 | 1/13/04 | |
| 46 | FM 2 Logic Board w/Flight ACTEL Functionally Tested | 12/26/03 | 1/13/04 | |
| 47 | FM 1 Ready for Delivery | 1/2/04 | 1/19/04 | |
| 48 | Deliver FM 1 for SEP I & T | 1/6/04 | 1/19/04 | |
| 49 | FM 2 Ready for Delivery | 1/15/04 | 1/29/04 | |
| 50 | Deliver FM 2 for SEP I & T | 1/15/04 | 1/29/04 |