| ITEM | EVENT | Require Action | ||
|---|---|---|---|---|
| 1 | Electronic Long Lead Procurements | 2/6/03 | 5/6/03 | |
| 2 | Procure SEPT Solid State Detectors | 2/28/03 | 3/3/03 | |
| 3 | Fabricate SEPT ETU Electronics Board | 3/13/03 | ||
| 4 | SEPT Mechanical Long Lead Procurements | 3/27/03 | 5/16/03 | |
| 5 | Assemble SEPT ETU Electronics Board | 3/27/03 | ||
| 6 | PDFE ASIC Manufacturing | 4/14/03 | 5/14/03 | |
| 7 | Fabricate SEPT-NS FM 1 N-S Brackets | 4/16/03 | 8/13/03 | |
| 8 | Fabricate SEPT-NS FM 2 N-S Brackets | 4/16/03 | 8/13/03 | |
| 9 | Assemble SEPT ETU Sensor and E-Box Housing | 4/17/03 | 8/19/03 | |
| 10 | ETU Tested | 4/24/03 | 8/22/03 | |
| 11 | SEPT ETU Electronics Test | 4/24/03 | ||
| 12 | Power supply testing | 4/25/03 | 5/23/03 | |
| 13 | Fabricate SEPT-NS FM 1 Electronics Board | 5/2/03 | 5/19/03 | |
| 14 | Fabricate SEPT-E FM 1 Electronics Board | 5/2/03 | 5/19/03 | |
| 15 | Fabricate SEPT-NS FM 2 Electronics Board | 5/2/03 | 5/19/03 | |
| 16 | Fabricate SEPT-E FM 2 Electronics Board | 5/2/03 | 5/19/03 | |
| 17 | PDFE ASIC Packaging | 6/2/03 | 7/2/03 | |
| 18 | ETU Delivered | 6/11/03 | ||
| 19 | ETU I & T Complete | 6/11/03 | 8/27/03 | |
| 20 | PDFE ASIC Testing, Screening | 6/23/03 | 7/23/03 | |
| 21 | Assemble SEPT-NS FM 1 Electronics | 6/27/03 | ||
| 22 | Assemble SEPT-E FM 1 Electronics | 6/27/03 | 7/29/03 | |
| 23 | Assemble SEPT-NS FM 2 Electronics | 6/27/03 | 7/29/03 | |
| 24 | Assemble SEPT-E FM 2 Electronics | 6/27/03 | 7/29/03 | |
| 25 | SEPT-NS FM 2 Electronics Test | 7/24/03 | 8/25/03 | |
| 26 | SEPT-E FM 2 Electronics Test | 7/24/03 | 8/25/03 | |
| 27 | SEPT-NS FM 1 Electronics Test | 7/25/03 | ||
| 28 | SEPT-E FM 1 Electronics Test | 7/25/03 | 8/26/03 | |
| 31 | Fabricate SEPT-NS FM 2 Sensor and E-Box Housing | 8/1/03 | 9/4/03 | |
| 32 | Fabricate SEPT-E FM 2 Sensor and E-Box Housing | 8/1/03 | 9/4/03 | |
| 33 | SEPT-NS FM 1 Mechanical Integration | 8/14/03 | ||
| 34 | SEPT-E FM 1 Mechanical Integration | 8/14/03 | 9/15/03 | |
| 35 | SEPT-NS FM 2 Mechanical Integration | 8/14/03 | 9/15/03 | |
| 36 | SEPT-E FM 2 Mechanical Integration | 8/14/03 | 9/15/03 | |
| 37 | Assemble SEPT-NS FM 1 Sensor and E-Box Housing | 8/29/03 | 9/2/03 | |
| 38 | Assemble SEPT-E FM 1 Sensor and E-Box Housing | 8/29/03 | 9/2/03 | |
| 39 | Assemble SEPT-NS FM 2 Sensor and E-Box Housing | 8/29/03 | 10/2/03 | |
| 40 | Assemble SEPT-E FM 2 Sensor and E-Box Housing | 8/29/03 | 10/2/03 | |
| 41 | ETU Environmentally Tested | 7/17/03 | 9/3/03 | |
| 42 | FM 1 NS I & T Complete | 9/26/03 | 9/30/03 | |
| 43 | FM 1 E I & T Complete | 9/26/03 | 10/14/03 | |
| 44 | FM 2 NS I & T Complete | 10/15/03 | 10/21/03 | |
| 45 | FM 2 E I & T Complete | 10/15/03 | 10/28/03 | |
| 46 | FM 1 NS Environmentally Tested | 10/27/03 | 10/29/03 | |
| 47 | FM 1 E Environmentally Tested | 10/27/03 | 11/11/03 | |
| 48 | FM 1 NS Delivered | 10/29/03 | 11/3/03 | |
| 49 | FM 1 E Delivered | 11/3/03 | 11/11/03 | |
| 50 | FM 2 NS Environmentally Tested | 11/12/03 | 11/18/03 | |
| 51 | FM 2 E Environmentally Tested | 11/12/03 | 11/25/03 | |
| 52 | FM 2 NS Delivered | 11/17/03 | 11/18/03 | |
| 53 | FM 2 E Delivered | 11/17/03 | 11/25/03 |