Instrument Milestones

Project Start Date: 11/1/02

Project End Date: 10/31/04

File Name: c:\STEREO\Bnets\SummaryCharts\2003_05_31_IMPACT SEPT Instrument Critical Milestone Chart.ML7

ITEM EVENT Require Action
1 Electronic Long Lead Procurements
2/6/03 5/6/03
2 Procure SEPT Solid State Detectors
2/28/03 3/3/03
3 Fabricate SEPT ETU Electronics Board
3/13/03
4 SEPT Mechanical Long Lead Procurements
3/27/03 5/16/03
5 Assemble SEPT ETU Electronics Board
3/27/03
6 PDFE ASIC Manufacturing
4/14/03 5/14/03
7 Fabricate SEPT-NS FM 1 N-S Brackets
4/16/03 8/13/03
8 Fabricate SEPT-NS FM 2 N-S Brackets
4/16/03 8/13/03
9 Assemble SEPT ETU Sensor and E-Box Housing
4/17/03 8/19/03
10 ETU Tested
4/24/03 8/22/03
11 SEPT ETU Electronics Test
4/24/03
12 Power supply testing
4/25/03 5/23/03
13 Fabricate SEPT-NS FM 1 Electronics Board
5/2/03 5/19/03
14 Fabricate SEPT-E FM 1 Electronics Board
5/2/03 5/19/03
15 Fabricate SEPT-NS FM 2 Electronics Board
5/2/03 5/19/03
16 Fabricate SEPT-E FM 2 Electronics Board
5/2/03 5/19/03
17 PDFE ASIC Packaging
6/2/03 7/2/03
18 ETU Delivered
6/11/03
19 ETU I & T Complete
6/11/03 8/27/03
20 PDFE ASIC Testing, Screening
6/23/03 7/23/03
21 Assemble SEPT-NS FM 1 Electronics
6/27/03
22 Assemble SEPT-E FM 1 Electronics
6/27/03 7/29/03
23 Assemble SEPT-NS FM 2 Electronics
6/27/03 7/29/03
24 Assemble SEPT-E FM 2 Electronics
6/27/03 7/29/03
25 SEPT-NS FM 2 Electronics Test
7/24/03 8/25/03
26 SEPT-E FM 2 Electronics Test
7/24/03 8/25/03
27 SEPT-NS FM 1 Electronics Test
7/25/03
28 SEPT-E FM 1 Electronics Test
7/25/03 8/26/03






31 Fabricate SEPT-NS FM 2 Sensor and E-Box Housing
8/1/03 9/4/03
32 Fabricate SEPT-E FM 2 Sensor and E-Box Housing
8/1/03 9/4/03
33 SEPT-NS FM 1 Mechanical Integration
8/14/03
34 SEPT-E FM 1 Mechanical Integration
8/14/03 9/15/03
35 SEPT-NS FM 2 Mechanical Integration
8/14/03 9/15/03
36 SEPT-E FM 2 Mechanical Integration
8/14/03 9/15/03
37 Assemble SEPT-NS FM 1 Sensor and E-Box Housing
8/29/03 9/2/03
38 Assemble SEPT-E FM 1 Sensor and E-Box Housing
8/29/03 9/2/03
39 Assemble SEPT-NS FM 2 Sensor and E-Box Housing
8/29/03 10/2/03
40 Assemble SEPT-E FM 2 Sensor and E-Box Housing
8/29/03 10/2/03
41 ETU Environmentally Tested
7/17/03 9/3/03
42 FM 1 NS I & T Complete
9/26/03 9/30/03
43 FM 1 E I & T Complete
9/26/03 10/14/03
44 FM 2 NS I & T Complete
10/15/03 10/21/03
45 FM 2 E I & T Complete
10/15/03 10/28/03
46 FM 1 NS Environmentally Tested
10/27/03 10/29/03
47 FM 1 E Environmentally Tested
10/27/03 11/11/03
48 FM 1 NS Delivered
10/29/03 11/3/03
49 FM 1 E Delivered
11/3/03 11/11/03
50 FM 2 NS Environmentally Tested
11/12/03 11/18/03
51 FM 2 E Environmentally Tested
11/12/03 11/25/03
52 FM 2 NS Delivered
11/17/03 11/18/03
53 FM 2 E Delivered
11/17/03 11/25/03

SEPT001.png

SEPT002.png

SEPT003.png

SEPT004.png