Project Start Date: 11/1/02

Project End Date: 10/31/04

File Name: c:\STEREO\Bnets\SummaryCharts\2003_05_31_IMPACT SEP Cen Instrument Critical Milestone Chart.ML7

ITEM EVENT Require Action
1 EM Logic Board Fabricated
3/19/03
2 EM Analog/Post-reg Board Fabricated
3/28/03
3 EM Solid State Detector Bias Supply Board Fabricated
4/2/03
4 B1 Flight Software Available
4/8/03
5 EM Analog/Post-reg Board Assembled
4/11/03 4/14/03
6 EM Logic Board Assembled
4/14/03 5/13/03
7 ETU LVPS Received
5/5/03 7/21/03
8 EM Logic Board Tested
5/5/03 5/8/03
9 ETU LVPS Tested
5/14/03 7/31/03
10 FM 1 SEP Central Common Enclosure Fabricated
5/22/03 8/12/03
11 FM 2 SEP Central Common Enclosure Fabricated
5/22/03 8/12/03
12 EM Analog/Post-reg Board Tested
5/28/03 6/5/03
13 EM Solid State Detector Bias Supply Board Tested
5/28/03 6/25/03
14 EM Boards Available for EM I & T
5/29/03 6/25/03
15 FM 1 SEP Central Common Electronics Enclosesure Assembled
5/30/03 8/19/03
16 FM 2 SEP Central Common Electronics Encloure Assembled
5/30/03 8/19/03
17 B2 Flight Software Available
7/7/03 7/29/03
18 Flight Logic Boards Fabricated
7/28/03 8/11/03
19 Flight Logic Boards Assembled
9/17/03 9/19/03
20 Flight Analog/Post-reg Boards Fabricated
8/25/03 9/23/03
21 Flight Solid State Detector Bias Supply Boards Fabricated
9/29/03 10/9/03
22 Flight Analog/Post-reg Board Assembled
9/4/03 10/2/03
23 FM 1 LVPS Received
10/13/03 11/20/03
24 Flight Logic Boards Tested
10/28/03 10/30/03
25 Flight Analog/Post-reg Boards Tested
10/27/03 11/25/03
26 Flight Solid State Detector Bias Supply Boards Tested
12/9/03 12/18/03
27 FM 1 LVPS Tested
12/11/03
28 FM 1 Ready for I & T
12/12/03
29 FM 2 LVPS Received
12/17/03 2/19/04
30 B3 Flight Software Available W/User Manual
12/18/03
31 FM 2 Ready for I & T
1/2/04 3/5/04
32 FM 2 LVPS Tested
1/2/04 3/5/04
33 Final Flight Software Available
1/7/04 1/30/04