Instrument Milestones

Project Start Date: 11/1/02

Project End Date: 10/31/04

File Name: c:\STEREO\Bnets\SummaryCharts\2003_05_31_IMPACT PS Instrument Critical Milestone Chart.ML7

ITEM EVENT Require Action
1 IDPU ETU LVPS Assembled
1/21/03
2 IDPU ETU LVPS Tested
2/3/03 2/5/03
3 IDPU ETU LVPS Delivered
2/5/03 2/10/03
4 SIT Flight HVPS Printed Wiring Boards Ordered
2/18/03 4/14/03
5 SIT FM 1 HVPS Assembled
3/14/03 6/13/03
6 SIT FM 1 HVPS Tested
3/21/03 6/20/03
7 SWEA/STE-D ETU LVPS Printed Wiring Board Fabricated
3/24/03 4/14/03
8 PLASTIC ETU LVPS Printed Wiring Board Fabricated
3/25/03 4/14/03
9 SIT FM 1 HVPS Delivered
3/31/03 6/30/03
10 SWEA/STE-D ETU LVPS Assembled
4/4/03 4/29/03
11 SEP ETU LVPS Printed Wiring Board Fabricated
4/7/03 6/20/03
12 PLASTIC ETU LVPS Assembled
4/7/03 6/6/03
13 IDPU FM 1 LVPS Assembled
4/17/03 7/9/03
14 SWEA/STE-D ETU LVPS Delivered
4/18/03 5/14/03
15 SWEA/STE-D ETU LVPS Tested
4/18/03 5/14/03
16 SEP ETU LVPS Assembled
4/21/03 7/7/03
17 PLASTIC ETU LVPS Tested
4/21/03 6/20/03
18 IDPU FM 1 LVPS Tested
5/1/03 7/23/03
19 SEP ETU LVPS Delivered
5/5/03 7/21/03
20 SEP ETU LVPS Tested
5/5/03 7/21/03
21 PLASTIC ETU LVPS Delivered
6/9/03 6/20/03
22 SWEA/STE-D FM 1 LVPS Assembled
7/14/03 9/8/03
23 IDPU FM 2 LVPS Assembled
7/14/03 10/2/03
24 SIT FM 2 HVPS Assembled
7/21/03 8/22/03
25 SIT FM 2 HVPS Tested
7/28/03 8/29/03
26 SWEA/STE-D FM 1 LVPS Tested
7/28/03 9/22/03
27 IDPU FM 2 LVPS Tested
7/28/03 10/17/03
28 SEP FM 1 LVPS Assembled
8/1/03 10/8/03
29 SIT FM 2 HVPS Delivered
8/5/03 9/9/03
30 SEP FM 1 LVPS Tested
8/15/03 10/22/03
31 PLASTIC FM 1 LVPS Assembled
8/25/03
32 PLASTIC FM 1 LVPS Tested
9/9/03
33 IDPU FM 1 LVPS Delivered
8/20/03 10/8/03
34 PLASTIC FM 1 LVPS Delivered
10/8/03
35 SWEA/STE-D FM 2 LVPS Assembled
10/8/03 12/4/03
36 SEP FM 1 LVPS Delivered
10/13/03 11/20/03
37 SWEA/STE-D FM 1 LVPS Delivered
10/14/03 10/21/03
38 SWEA/STE-D FM 2 LVPS Tested
10/22/03 12/18/03
39 SEP FM 2 LVPS Assembled
10/28/03 1/6/04
40 SEP FM 2 LVPS Tested
11/12/03 1/21/04
41 PLASTIC FM 2 LVPS Assembled
11/19/03
42 PLASTIC FM 2 LVPS Tested
12/4/03
43 SEP FM 2 LVPS Delivered
12/17/03 2/19/04
44 IDPU FM 2 LVPS Delivered
11/17/03 1/5/04
45 PLASTIC FM 2 LVPS Delivered
1/5/04
46 SWEA/STE-D FM 2 LVPS Delivered
1/9/04 1/20/04