ITEM EVENT Require Action
1 Deliver ETU For IDPU I/F Testing
1/20/03
2 Long Lead Procurements Complete
3/11/03 4/9/03
3 FM 1 PWB Fabricated
3/12/03 7/31/03
4 FM 2 PWB Fabricated
3/12/03 7/31/03
5 FM 1 PWB Coupon Tested
4/2/03 8/14/03
6 FM 2 PWB Coupon Tested
4/2/03 8/14/03
7 FM 1 Analog Board Loaded
4/29/03 8/28/03
8 FM 1 Tested
5/12/03 9/12/03
9 FM 1 Calibrated
5/27/03 9/19/03
10 FM 2 Analog Board Loaded
6/24/03 9/12/03
11 Deliver FM 1
6/30/03 10/3/03
12 FM 2 Tested
7/9/03 9/26/03
13 FM 2 Calibrated
7/23/03 10/3/03
14 Deliver FM 2
11/18/03 12/1/03