Instrument Milestones

Project Start Date: 11/1/02

Project End Date: 10/31/04

File Name: c:\STEREO\Bnets\SummaryCharts\2003_05_31_IMPACT LET Instrument Critical Milestone Chart.ML7

ITEM EVENT Require Action
1 L1 Detector Decision
1/31/03
2 B1 Flight S/W
2/5/03 3/5/03
3 Order Flight Detectors
2/19/03 3/3/03
4 EM Detector Board Designed
3/13/03 5/1/03
5 EM Detector Board Fabricated
4/15/03 5/20/03
6 B2 Flight S/W
5/28/03 7/2/03
7 EM Detector Board Tested
6/26/03 7/16/03
8 EM Delivery For SEP Package EM I & T
6/30/03 7/18/03
9 Flight Detector Board Design Rework
7/24/03 8/12/03
10 Flight Detector Boards Fabricated & Inspected
8/21/03 9/10/03
11 All Flight Detectors Received
9/18/03 9/30/03
12 FM 1 Detector Board Assembled
9/26/03 10/16/03
13 FM 2 Detector Board Assembled
9/26/03 10/16/03
14 Flight Detectors Life Tested
10/30/03
15 B3 Flight S/W
11/3/03 12/10/03
16 FM1 Detector Board Tested
11/19/03 12/9/03
17 FM 2 Detector Board Tested
11/19/03 12/9/03
18 FM 1 Integrated & Tested
12/29/03 12/30/03
19 FM1 Delivery for SEP Package I & T
12/29/03 12/31/03
20 FM 2 Integrated and Tested
12/29/03 12/30/03
21 FM 2 Delivery for SEP Package I & T
12/29/03 12/31/03