ITEM | EVENT | Require Action | ||
---|---|---|---|---|
1 | L1 Detector Decision | 1/31/03 | ||
2 | B1 Flight S/W | 2/5/03 | 3/5/03 | |
3 | Order Flight Detectors | 2/19/03 | 3/3/03 | |
4 | EM Detector Board Designed | 3/13/03 | 5/1/03 | |
5 | EM Detector Board Fabricated | 4/15/03 | 5/20/03 | |
6 | B2 Flight S/W | 5/28/03 | 7/2/03 | |
7 | EM Detector Board Tested | 6/26/03 | 7/16/03 | |
8 | EM Delivery For SEP Package EM I & T | 6/30/03 | 7/18/03 | |
9 | Flight Detector Board Design Rework | 7/24/03 | 8/12/03 | |
10 | Flight Detector Boards Fabricated & Inspected | 8/21/03 | 9/10/03 | |
11 | All Flight Detectors Received | 9/18/03 | 9/30/03 | |
12 | FM 1 Detector Board Assembled | 9/26/03 | 10/16/03 | |
13 | FM 2 Detector Board Assembled | 9/26/03 | 10/16/03 | |
14 | Flight Detectors Life Tested | 10/30/03 | ||
15 | B3 Flight S/W | 11/3/03 | 12/10/03 | |
16 | FM1 Detector Board Tested | 11/19/03 | 12/9/03 | |
17 | FM 2 Detector Board Tested | 11/19/03 | 12/9/03 | |
18 | FM 1 Integrated & Tested | 12/29/03 | 12/30/03 | |
19 | FM1 Delivery for SEP Package I & T | 12/29/03 | 12/31/03 | |
20 | FM 2 Integrated and Tested | 12/29/03 | 12/30/03 | |
21 | FM 2 Delivery for SEP Package I & T | 12/29/03 | 12/31/03 |