| ITEM | EVENT | ||
|---|---|---|---|
| 1 | IMPACT - Instrument CDR | 11/22/02 | |
| 2 | MAG - Deliver ETU to UC-B | 1/20/03 | |
| 3 | IMPACT - Flight ACTEL Lot Buy Received | 1/20/03 | |
| 4 | LET - L1 Detector Decision Trigger Event | 1/31/03 | |
| 5 | HET - Place Flight Detector Order | 2/5/03 | 2/19/03 |
| 6 | IMPACT - Flight ACTEL Lot DPA Complete | 2/7/03 | |
| 7 | IDPU - ETU LVPS Available | 2/5/03 | 2/10/03 |
| 8 | IDPU - ETU Complete (Final Testing) | 2/15/03 | 2/25/03 |
| 9 | LET - Place Flight Detector Order | 2/19/03 | 3/3/03 |
| 10 | SWEA/STE-D - ETU LVPS Available | 4/18/03 | 5/14/03 |
| 11 | STE -ETU Complete | 4/24/03 | 6/12/03 |
| 12 | SWEA - ETU Complete | 5/2/03 | 6/27/03 |
| 13 | SEP - ETU LVPS Available | 5/5/03 | 7/21/03 |
| 14 | HET - Deliver EM to CIT | 5/13/03 | 6/17/03 |
| 15 | SEP Central - EM Ready for I & T | 5/29/03 | 6/25/03 |
| 16 | PLASTIC - ETU LVPS Available | 6/9/03 | 6/20/03 |
| 17 | SEPT - Deliver ETU to CIT | 6/11/03 | |
| 18 | SIT - Deliver EM to CIT | 6/13/03 | |
| 19 | MAG - Deliver FM 1 to UC-B | 6/30/03 | 10/3/03 |
| 20 | Boom - Completion of Boom Protoflight Unit | 7/16/03 | 7/23/03 |
| 21 | SIT - FM 1 Digital TOF Boards Available | 7/21/03 | 8/18/03 |
| 22 | SIT - FM 1 Analog TOF Boards Available | 7/28/03 | 8/18/03 |
| 23 | SIT - FM 2 Digital TOF Boards Available | 7/28/03 | 8/18/03 |
| 24 | SIT - FM 2 Analog TOF Boards Available | 7/28/03 | 8/18/03 |
| 25 | IMPACT - Instrument PER | 8/25/03 | |
| 26 | HET - All Flight Detectors Received | 9/8/03 | 9/22/03 |
| 27 | LET - All Flight Detectors Received | 9/18/03 | 9/30/03 |
| 28 | SEP Package - EM I & T Complete | 9/5/03 | 10/2/03 |
| 29 | IMPACT - FM 1 Power Supplies Complete | 10/14/03 | 11/20/03 |
| 30 | SEPT - NS FM 1 Delivery to CIT for SEP I & T | 10/29/03 | 11/3/03 |
| 31 | SEPT - E FM 1 Delivery to CIT for SEP I & T | 11/3/03 | 11/11/03 |
| 32 | SWEA - FM 1 Detectors/Front-End to UC-B | 11/13/03 | 11/17/03 |
| 33 | SEPT - NS FM 2 Delivery to CIT for SEP I & T | 11/17/03 | 11/18/03 |
| 34 | SEPT - E FM 2 Delivery to CIT for SEP I & T | 11/17/03 | 11/25/03 |
| 35 | SEP Central - FM 1 Ready for I & T | 12/12/03 | |
| 36 | MAG - Deliver FM 2 to UC-B | 11/18/03 | 12/1/03 |
| 37 | HET - FM 1 Delivery for SEP I & T | 12/23/03 | 1/8/04 |
| 38 | LET - FM 1 Delivery to SEP I & T | 12/29/03 | 12/31/03 |
| 39 | LET - FM 2 Delivery to SEP I & T | 12/29/03 | 12/31/03 |
| 40 | SEP Central - FM 2 Ready for I & T | 1/2/04 | 3/5/04 |
| 41 | SIT - FM 1 Delivery to CIT For SEP I & T | 1/6/04 | 1/19/04 |
| 42 | STE-U - FM 1 Complete | 1/7/04 | 1/8/04 |
| 43 | IMPACT - FM 2 Power Supplies Complete | 1/9/04 | 2/19/04 |
| 44 | SIT - FM 2 Delivery to CIT For SEP I & T | 1/15/04 | 1/29/04 |
| 45 | HET - FM 2 Delivery for SEP I & T | 1/22/04 | 2/3/04 |
| 46 | SWEA - FM 1 Complete | 1/28/04 | 2/23/04 |
| 47 | IDPU - FM 1 Ready For Boom Suite I & T | 2/10/04 | |
| 48 | SWEA - FM 2 Detectors/Front-End to UC-B | 2/16/04 | |
| 49 | Boom Suite - FM 1 I & T Complete | 4/1/04 | 4/12/04 |
| 50 | SEP Package - FM 2 I & T Complete | 4/7/04 | 4/20/04 |
| 51 | SEP Package - FM 1 I & T Complete | 4/8/04 | 4/21/04 |
| 52 | IDPU - FM 2 Ready For Boom Suite I & T | 4/8/04 | 4/21/04 |
| 53 | STE-U - FM 2 Complete | 4/19/04 | |
| 54 | SWEA - FM 2 Complete | 5/3/04 | 5/4/04 |
| 55 | IMPACT - Suite FM 1 EMC Testing Complete | 5/7/04 | 5/14/04 |
| 56 | SEP Package - FM 2 EMC Testing Complete | 5/14/04 | 5/21/04 |
| 57 | Boom Suite - FM 1 Environmental Testing Complete | 5/18/04 | 5/25/04 |
| 58 | Boom Suite - FM 2 I & T Complete | 5/17/04 | 6/4/04 |
| 59 | Boom - FM 1 Structure Delivered | 6/7/04 | 6/14/04 |
| 60 | Boom Suite - FM 2 Environmental Testing Complete | 5/19/04 | 6/8/04 |
| 61 | Boom Suite - FM 2 EMC Testing Complete | 5/28/04 | 6/15/04 |
| 62 | SEP Package - FM 1 Enviornmental Testing Complete | 7/1/04 | 7/9/04 |
| 63 | Boom - FM 2 Structure Delivered | 7/6/04 | 7/13/04 |
| 64 | SEP Package - FM 1 Ready For Delivery | 7/7/04 | 7/14/04 |
| 65 | BOOM Suite - FM 1 Ready For Delivery | 6/24/04 | 7/14/04 |
| 66 | BOOM Suite - FM 2 Ready For Delivery | 6/28/04 | 7/27/04 |
| 67 | SEP Package - FM 2 Ready For Delivery | 7/28/04 | |
| 68 | BOOM Suite - FM 1 Delivery to APL | 8/13/04 | 9/1/04 |
| 69 | SEP Package - FM 1 Delivery to APL | 9/1/04 | |
| 70 | BOOM Suite - FM 2 Delivery to APL | 8/17/04 | 9/15/04 |
| 71 | SEP Package - Delivery FM 2 to APL | 9/15/04 |