Instrument Milestones

Project Start Date: 11/1/02

Project End Date: 10/31/04

File Name: c:\STEREO\Bnets\SummaryCharts\2003_05_31_IMPACT IDPU Instrument Critical Milestone Chart.ML7

ITEM EVENT Require Action
1 Reworked S/W Build 1
1/15/03
2 ETU MAG For ETU I & T Received
1/20/03
3 MAG ETU Integrated and Tested
1/27/03
4 ETU LVPS Received
2/5/03 2/10/03
5 IDPU - ETU Complete (Final Testing)
2/15/03 2/25/03
6 ETU LVPS Integrated & Tested
2/10/03 2/25/03
7 Build 2.0 Complete
4/3/03 4/22/03
8 ETU SWEA/STE-D I/F For ETU I & T Received
5/2/03 6/27/03
9 ETU SWEA/STE-D Integrated & Tested
5/16/03 7/14/03
10 FM 1 MAG For ETU I & T Received
7/8/03 10/13/03
11 FM 1 IDPU Box Fabricated
6/27/03 7/14/03
12 FM 1 IDPU Data Control Board Loaded
6/13/03 7/28/03
13 Build 2.5 Complete
9/11/03 9/12/03
14 FM 1 LVPS Received
8/20/03 10/8/03
15 FM 1 IDPU Integrated & Tested
11/5/03 12/12/03
16 FM 2 IDPU Data Control Board Loaded
11/20/03 12/29/03
17 FM 2 MAG For ETU I & T Received
11/25/03 12/8/03
18 FM 1 IDPU Environmentally Tested
12/11/03 1/20/04
19 FM 2 IDPU Box Fabricated
12/26/03 2/3/04
20 FM 2 LVPS Received
11/17/03 1/5/04
21 Build 3.0 Complete
1/8/04 1/9/04
22 FM 2 IDPU Integrated & Tested
1/19/04 2/17/04
23 FM 1 Ready
2/10/04
24 FM 1 IDPU Delivery for BOOM Suite I & T
2/10/04
25 FM 2 IDPU Environmentally Tested
2/24/04 3/23/04
26 FM 2 Ready
3/30/04
27 FM 2 IDPU Delivery for BOOM Suite I & T
4/8/04 4/21/04