| ITEM | EVENT | Require Action | ||
|---|---|---|---|---|
| 1 | Place Flight Detector Order | 2/5/03 | 2/19/03 | |
| 2 | Flight Detectors Ordered | 2/6/03 | 2/19/03 | |
| 3 | FM 1 Housing Fabricated and Inspected | 3/18/03 | 7/2/03 | |
| 4 | FM 2 Housing Fabricated and Inspected | 3/18/03 | 7/2/03 | |
| 5 | Spare Housing Fabricated and Inspected | 3/18/03 | 7/2/03 | |
| 6 | EM Electronics Board Fabricated | 3/19/03 | 4/7/03 | |
| 7 | EM Electronics Board Assembled | 4/1/03 | 4/14/03 | |
| 8 | Deliver EM to CIT | 5/13/03 | 6/17/03 | |
| 10 | S/W Delivery for SEP Central MISC/HET CPU24 Testing | 5/28/03 | 6/21/07 | |
| 11 | Flight S/W Tested | 5/28/03 | 9/8/03 | |
| 12 | FM 1 Electronics Board Fabricated | 7/24/03 | 8/13/03 | |
| 13 | FM 2 Electronics Board Fabricated | 7/24/03 | 8/13/03 | |
| 14 | FM 1 Electronics Board Assembled | 8/6/03 | 8/26/03 | |
| 15 | FM 2 Electronics Board Assembled | 8/19/03 | 9/9/03 | |
| 16 | FM 1 Electronics Board Tested | 9/4/03 | 10/7/03 | |
| 17 | All Flight Detectors Received | 9/8/03 | 9/22/03 | |
| 18 | FM 2 Electronics Board Tested | 10/16/03 | 11/18/03 | |
| 19 | Flight Detector Testing Completed | 10/21/03 | 10/30/03 | |
| 20 | FM 1 Telescope Assembled without Electronics | 11/3/03 | 11/13/03 | |
| 21 | FM 2 Telescope Assembled without Electronics | 11/3/03 | 11/13/03 | |
| 22 | FM 1 Electronics Board Available | 11/6/03 | 12/10/03 | |
| 23 | FM 2 Electronics Board Available | 11/14/03 | 12/17/03 | |
| 24 | FM 1 Telescope Structure Available | 11/18/03 | 11/28/03 | |
| 25 | FM 2 Telescope Structure Available | 11/18/03 | 11/28/03 | |
| 26 | FM 1 Telescope Integrated | 11/25/03 | 12/17/03 | |
| 27 | FM 2 Telescope Integrated | 12/3/03 | 12/24/03 | |
| 28 | FM 1 Telescope Ready For Delivery | 12/23/03 | 1/8/04 | |
| 29 | FM 1 Delivery for SEP I & T | 12/23/03 | 1/8/04 | |
| 30 | FM 2 Telescope Ready For Delivery | 1/22/04 | 2/3/04 | |
| 31 | FM 2 Delivery for SEP I & T | 1/22/04 | 2/3/04 |