Instrument Milestones

Project Start Date: 11/1/02

Project End Date: 10/31/04

File Name: c:\STEREO\Bnets\SummaryCharts\2003_05_31_IMPACT HET Instrument Critical Milestone Chart.ML7

ITEM EVENT Require Action
1 Place Flight Detector Order
2/5/03 2/19/03
2 Flight Detectors Ordered
2/6/03 2/19/03
3 FM 1 Housing Fabricated and Inspected
3/18/03 7/2/03
4 FM 2 Housing Fabricated and Inspected
3/18/03 7/2/03
5 Spare Housing Fabricated and Inspected
3/18/03 7/2/03
6 EM Electronics Board Fabricated
3/19/03 4/7/03
7 EM Electronics Board Assembled
4/1/03 4/14/03
8 Deliver EM to CIT
5/13/03 6/17/03



10 S/W Delivery for SEP Central MISC/HET CPU24 Testing
5/28/03 6/21/07
11 Flight S/W Tested
5/28/03 9/8/03
12 FM 1 Electronics Board Fabricated
7/24/03 8/13/03
13 FM 2 Electronics Board Fabricated
7/24/03 8/13/03
14 FM 1 Electronics Board Assembled
8/6/03 8/26/03
15 FM 2 Electronics Board Assembled
8/19/03 9/9/03
16 FM 1 Electronics Board Tested
9/4/03 10/7/03
17 All Flight Detectors Received
9/8/03 9/22/03
18 FM 2 Electronics Board Tested
10/16/03 11/18/03
19 Flight Detector Testing Completed
10/21/03 10/30/03
20 FM 1 Telescope Assembled without Electronics
11/3/03 11/13/03
21 FM 2 Telescope Assembled without Electronics
11/3/03 11/13/03
22 FM 1 Electronics Board Available
11/6/03 12/10/03
23 FM 2 Electronics Board Available
11/14/03 12/17/03
24 FM 1 Telescope Structure Available
11/18/03 11/28/03
25 FM 2 Telescope Structure Available
11/18/03 11/28/03
26 FM 1 Telescope Integrated
11/25/03 12/17/03
27 FM 2 Telescope Integrated
12/3/03 12/24/03
28 FM 1 Telescope Ready For Delivery
12/23/03 1/8/04
29 FM 1 Delivery for SEP I & T
12/23/03 1/8/04
30 FM 2 Telescope Ready For Delivery
1/22/04 2/3/04
31 FM 2 Delivery for SEP I & T
1/22/04 2/3/04