| ITEM | EVENT | Require Action | ||
|---|---|---|---|---|
| 1 | Protoflight Tubes Ordered | 1/24/03 | ||
| 2 | Stacer Ordered | 1/29/03 | ||
| 3 | Pin Puller Ordered | 1/31/03 | ||
| 4 | Protoflight Design Reviewed | 2/26/03 | 4/1/03 | |
| 5 | Protoflight Mountings Designed | 3/10/03 | 4/4/03 | |
| 6 | Other Protoflight Telescoping Parts Fabricated | 3/21/03 | 4/10/03 | |
| 7 | Protoflight Tubes Received & Inspected | 3/26/03 | 5/2/03 | |
| 8 | Stacer Received & Inspected | 4/1/03 | 4/2/03 | |
| 9 | Protoflight Mountings Fabricated | 4/7/03 | 5/14/03 | |
| 10 | Protoflight Mountings Assembled | 4/14/03 | 5/21/03 | |
| 11 | Protoflight Telescoping Boom Assembled | 4/16/03 | 5/22/03 | |
| 12 | Protoflight Mountings Fit Checked | 4/21/03 | 5/29/03 | |
| 13 | Protoflight Telescoping Boom Subassembly Tested | 4/23/03 | 5/30/03 | |
| 14 | Protoflight Test Preparation Workshop | 4/24/03 | 6/4/03 | |
| 15 | Pin Puller Received & Inspected | 4/30/03 | 6/4/03 | |
| 16 | Boom Structure Blanket Mockup Delivered to APL | 5/9/03 | ||
| 17 | Protoflight Boom Integrated | 5/14/03 | 6/6/03 | |
| 18 | Protoflight Deployment Test Complete | 5/21/03 | 6/13/03 | |
| 19 | Protoflight Boom Vibration Test Complete | 5/23/03 | 6/17/03 | |
| 20 | Protoflight Boom Themal Vac Testing Complete | 6/16/03 | 7/9/03 | |
| 21 | Protoflight Boom Post Environmental Deployment Test | 6/18/03 | 7/16/03 | |
| 22 | Order Flight Tubes | 6/19/03 | 7/17/03 | |
| 23 | Protoflight Boom Thermal Balance Testing | 6/30/03 | 7/14/03 | |
| 24 | Protoflight Boom Complete | 7/16/03 | 7/23/03 | |
| 25 | Harness Design Reworked (if necessary) | 7/17/03 | 8/13/03 | |
| 26 | Mounting Design Reworked (if necessary) | 7/24/03 | 8/20/03 | |
| 27 | Protoflight Test Results Workshop and Deployment Demo | 7/10/03 | 7/24/03 | |
| 28 | Flight Tubes Received & Inspected | 8/5/03 | 9/2/03 | |
| 29 | FM 1 Harness Parts Fabricated | 8/21/03 | 9/18/03 | |
| 30 | FM 1 Boom Structure Mounting Fabricated | 8/21/03 | 9/18/03 | |
| 31 | FM 2 Harness Parts Fabricated | 8/21/03 | 9/18/03 | |
| 32 | FM 2 Boom Structure Mounting Fabricated | 8/21/03 | 9/18/03 | |
| 33 | Telescoping Design Reworked (if necessary) | 8/27/03 | 9/4/03 | |
| 34 | Flight Model Design Update Workshop | 8/28/03 | 9/5/03 | |
| 35 | FM 1 Boom Structure Mounting Assemblies Assembled | 9/5/03 | 10/2/03 | |
| 36 | FM 2 Boom Structure Mounting Assemblies Assembled | 9/5/03 | 10/2/03 | |
| 37 | FM 1 Harness subassembly Assembled | 9/19/03 | 10/17/03 | |
| 38 | FM 1 Boom Structure Mountings Tested | 9/19/03 | 10/17/03 | |
| 39 | FM 2 Harness subassembly Assembled | 9/19/03 | 10/17/03 | |
| 40 | FM 2 Boom Structure Mountings Tested | 9/19/03 | 10/17/03 | |
| 41 | FM 1 Boom Structure Partes Fabricated | 10/2/03 | 10/10/03 | |
| 42 | FM 2 Boom Structure Partes Fabricated | 10/2/03 | 10/10/03 | |
| 43 | FM 2 Harness Tested | 10/3/03 | 10/31/03 | |
| 44 | Flight Boom Structure Status and Flight Testing Preparation Workshop | 10/20/03 | 10/27/03 | |
| 45 | FM 1 Boom Structure Telescoping Assembly Assembled | 10/31/03 | 11/7/03 | |
| 46 | FM 2 Boom Structure Telescoping Assembly Assembled | 10/31/03 | 11/7/03 | |
| 47 | FM 1 Boom Structure Telescoping Assembly Tested | 11/17/03 | 11/24/03 | |
| 48 | FM 2 Boom Structure Telescoping Assembly Tested | 11/17/03 | 11/24/03 | |
| 49 | FM 1 Boom Structure subassemblies Integrated | 12/16/03 | 12/23/03 | |
| 50 | FM 2 Boom Structure subassemblies Integrated | 12/16/03 | 12/23/03 | |
| 51 | Protoflight Boom Delivered for Boom Suite I & T | 12/30/03 | 12/31/03 | |
| 52 | FM 1 Boom Structure Deployment Testing Completed | 12/31/03 | 1/8/04 | |
| 53 | FM 2 Boom Structure Deployment Testing Completed | 12/31/03 | 1/8/04 | |
| 54 | FM 1 Boom Structure Vibration Test | 1/7/04 | 1/15/04 | |
| 55 | FM 2 Boom Structure Vibration Test | 1/7/04 | 1/15/04 | |
| 56 | FM 1 Boom Structure Themal Vac Testing | 2/20/04 | 2/27/04 | |
| 57 | FM 1 Boom Structure Post Environmental Deployment Test | 2/26/04 | 3/4/04 | |
| 58 | FM 2 Boom Structure Post Environmental Deployment Test | 2/26/04 | 3/4/04 | |
| 59 | Flight Model Boom Test Results Workshop | 3/5/04 | 3/12/04 | |
| 60 | FM 1 Boom Structure Complete | 3/11/04 | 3/18/04 | |
| 61 | FM 2 Boom Structure Complete | 3/11/04 | 3/18/04 | |
| 62 | FM 1 Boom Structure Ready for Delivery to APL | 6/7/04 | 6/14/04 | |
| 63 | FM 2 Boom Structure Ready for Delivery to APL | 7/6/04 | 7/13/04 |