ITEM | EVENT | Require Action | ||
---|---|---|---|---|
1 | Protoflight Tubes Ordered | 1/24/03 | ||
2 | Stacer Ordered | 1/29/03 | ||
3 | Pin Puller Ordered | 1/31/03 | ||
4 | Protoflight Design Reviewed | 2/26/03 | 4/1/03 | |
5 | Protoflight Mountings Designed | 3/10/03 | 4/4/03 | |
6 | Other Protoflight Telescoping Parts Fabricated | 3/21/03 | 4/10/03 | |
7 | Protoflight Tubes Received & Inspected | 3/26/03 | 5/2/03 | |
8 | Stacer Received & Inspected | 4/1/03 | 4/2/03 | |
9 | Protoflight Mountings Fabricated | 4/7/03 | 5/14/03 | |
10 | Protoflight Mountings Assembled | 4/14/03 | 5/21/03 | |
11 | Protoflight Telescoping Boom Assembled | 4/16/03 | 5/22/03 | |
12 | Protoflight Mountings Fit Checked | 4/21/03 | 5/29/03 | |
13 | Protoflight Telescoping Boom Subassembly Tested | 4/23/03 | 5/30/03 | |
14 | Protoflight Test Preparation Workshop | 4/24/03 | 6/4/03 | |
15 | Pin Puller Received & Inspected | 4/30/03 | 6/4/03 | |
16 | Boom Structure Blanket Mockup Delivered to APL | 5/9/03 | ||
17 | Protoflight Boom Integrated | 5/14/03 | 6/6/03 | |
18 | Protoflight Deployment Test Complete | 5/21/03 | 6/13/03 | |
19 | Protoflight Boom Vibration Test Complete | 5/23/03 | 6/17/03 | |
20 | Protoflight Boom Themal Vac Testing Complete | 6/16/03 | 7/9/03 | |
21 | Protoflight Boom Post Environmental Deployment Test | 6/18/03 | 7/16/03 | |
22 | Order Flight Tubes | 6/19/03 | 7/17/03 | |
23 | Protoflight Boom Thermal Balance Testing | 6/30/03 | 7/14/03 | |
24 | Protoflight Boom Complete | 7/16/03 | 7/23/03 | |
25 | Harness Design Reworked (if necessary) | 7/17/03 | 8/13/03 | |
26 | Mounting Design Reworked (if necessary) | 7/24/03 | 8/20/03 | |
27 | Protoflight Test Results Workshop and Deployment Demo | 7/10/03 | 7/24/03 | |
28 | Flight Tubes Received & Inspected | 8/5/03 | 9/2/03 | |
29 | FM 1 Harness Parts Fabricated | 8/21/03 | 9/18/03 | |
30 | FM 1 Boom Structure Mounting Fabricated | 8/21/03 | 9/18/03 | |
31 | FM 2 Harness Parts Fabricated | 8/21/03 | 9/18/03 | |
32 | FM 2 Boom Structure Mounting Fabricated | 8/21/03 | 9/18/03 | |
33 | Telescoping Design Reworked (if necessary) | 8/27/03 | 9/4/03 | |
34 | Flight Model Design Update Workshop | 8/28/03 | 9/5/03 | |
35 | FM 1 Boom Structure Mounting Assemblies Assembled | 9/5/03 | 10/2/03 | |
36 | FM 2 Boom Structure Mounting Assemblies Assembled | 9/5/03 | 10/2/03 | |
37 | FM 1 Harness subassembly Assembled | 9/19/03 | 10/17/03 | |
38 | FM 1 Boom Structure Mountings Tested | 9/19/03 | 10/17/03 | |
39 | FM 2 Harness subassembly Assembled | 9/19/03 | 10/17/03 | |
40 | FM 2 Boom Structure Mountings Tested | 9/19/03 | 10/17/03 | |
41 | FM 1 Boom Structure Partes Fabricated | 10/2/03 | 10/10/03 | |
42 | FM 2 Boom Structure Partes Fabricated | 10/2/03 | 10/10/03 | |
43 | FM 2 Harness Tested | 10/3/03 | 10/31/03 | |
44 | Flight Boom Structure Status and Flight Testing Preparation Workshop | 10/20/03 | 10/27/03 | |
45 | FM 1 Boom Structure Telescoping Assembly Assembled | 10/31/03 | 11/7/03 | |
46 | FM 2 Boom Structure Telescoping Assembly Assembled | 10/31/03 | 11/7/03 | |
47 | FM 1 Boom Structure Telescoping Assembly Tested | 11/17/03 | 11/24/03 | |
48 | FM 2 Boom Structure Telescoping Assembly Tested | 11/17/03 | 11/24/03 | |
49 | FM 1 Boom Structure subassemblies Integrated | 12/16/03 | 12/23/03 | |
50 | FM 2 Boom Structure subassemblies Integrated | 12/16/03 | 12/23/03 | |
51 | Protoflight Boom Delivered for Boom Suite I & T | 12/30/03 | 12/31/03 | |
52 | FM 1 Boom Structure Deployment Testing Completed | 12/31/03 | 1/8/04 | |
53 | FM 2 Boom Structure Deployment Testing Completed | 12/31/03 | 1/8/04 | |
54 | FM 1 Boom Structure Vibration Test | 1/7/04 | 1/15/04 | |
55 | FM 2 Boom Structure Vibration Test | 1/7/04 | 1/15/04 | |
56 | FM 1 Boom Structure Themal Vac Testing | 2/20/04 | 2/27/04 | |
57 | FM 1 Boom Structure Post Environmental Deployment Test | 2/26/04 | 3/4/04 | |
58 | FM 2 Boom Structure Post Environmental Deployment Test | 2/26/04 | 3/4/04 | |
59 | Flight Model Boom Test Results Workshop | 3/5/04 | 3/12/04 | |
60 | FM 1 Boom Structure Complete | 3/11/04 | 3/18/04 | |
61 | FM 2 Boom Structure Complete | 3/11/04 | 3/18/04 | |
62 | FM 1 Boom Structure Ready for Delivery to APL | 6/7/04 | 6/14/04 | |
63 | FM 2 Boom Structure Ready for Delivery to APL | 7/6/04 | 7/13/04 |